|
Now, let’s assume you did have a conversation with the sponsor
at the beginning of the project two months ago and your sponsor prioritized
the triple constraints as; Time, Resources, then Scope. You have
submitted a significant change request (10% overall increase) to
add resources to the project to ensure the project end date can be
obtained (the project schedule is slipping due to critical path activities
taking longer to complete than anticipated). Let’s assume your
sponsor has rejected the change request saying the project can not
exceed the currently allocated project budget due to recent budget
cuts. You then need to discuss with your sponsor the ability to change
the priority of the triple constraints. It’s apparent that
Resources (money) are now the highest of the triple constraints.
It’s impossible to meet the current end date with the current
allocation of resources and scope. You have already reduced scope
to the minimum acceptable level by the business areas (you already
did this because scope was the lowest prioritized triple constraint
agreed upon originally) – so your next logical option is to
move out the project end date. If you sponsor says “that’s
impossible” then you can remind him that you must “balance” between
the three triple constraints and “SOMETHING must give”.
It is essential for you to take a stand and remind your sponsor about
the critical balance between the triple constraints and work with
the sponsor to stabilize the project.
Conversations like this are
difficult, but they are essential for the ultimate success of the
project. Maybe the business areas can reduce scope some more. Is
there any chance some of the budget for the project can
be increased? In addition, maybe we get more internal resources
and remove some
of the project consultants that are more expensive. It’s time
to get creative – but it’s not appropriate to compromise
the concept behind the triple constraint. If you don’t push
back, your sponsor will assume you can “pull it off”.
It is not in the best interest of the project team (or the company)
to have people work even more overtime than they already are and/or
reduce the quality (i.e. testing, reviews, etc.) of the agreed upon
scope (which is typically what happens).
The prioritization of the triple constraints can, and will, change
throughout the life of the project. However, the prioritization should
not change frequently and you definitely don’t
want it going back-and-forth (i.e. Time is the #1 priority this week,
Resources
next week, and back to Time the following week). When the priority
does change (or appears to be changing based on the behavior you’re
observing from your sponsor), it should be confirmed via an overt
conversation with your sponsor. This will enable you to move forward
and to continue making daily decisions about your project based on
the new prioritization of the triple constraints.
As the project manager, it’s YOUR job to educate your sponsor
(and other key stakeholders) regarding the triple constraint concept
and to manage them effectively. Anyone can UNDERSTAND the triple
constraint concept; however, MANAGING the triple constraints successfully
is the hard part. It’s similar to a diet – the concept
of a diet is easy. If you consume less calories than you burn, you
will lose weight. Easy concept – extremely difficult to implement
successfully!
continue>>
<<back
|